Bangalore/Metro/Under Construction

Namma Metro Pink Line — Kalena Agrahara to Nagawara

21.25 km corridor running north-south through central Bangalore connecting Nagawara to Kalena Agrahara. Includes underground section through Shivajinagar and MG Road.

Key Facts

Status

Under Construction

Mode

Metro

Length

21.3 km

Stations

18

Progress

74%

Expected completion

Jul 2025

Approved cost

9,900 Cr

Current cost

11,000 Cr

Timeline

  1. Construction startMar 2018
  2. Original completion targetDec 2024
  3. Current completion targetJul 2025

Tenders and Contracts

NIT: BMRCL/Phase-2/Pink/UG/02
Cost: ₹2100 Crawarded

Design and Construction of Twin Tunnels and 12 Underground Stations for Pink Line

Floated: Sep 10, 2018
Awarded: Apr 12, 2019
Contractor: Afcons Infrastructure (Mumbai, Maharashtra)

Funding and Sources

Operator
Bangalore Metro Rail Corporation (BMRCL)
Funding source
mixed
Source
[Bangalore Metro Rail Corporation Limited (BMRCL)]Source Reference
Official Releasehigh Confidence