Bangalore/Metro/Under Construction
Namma Metro Pink Line — Kalena Agrahara to Nagawara
21.25 km corridor running north-south through central Bangalore connecting Nagawara to Kalena Agrahara. Includes underground section through Shivajinagar and MG Road.
Key Facts
Status
Under Construction
Mode
Metro
Length
21.3 km
Stations
18
Progress
74%
Expected completion
Jul 2025
Approved cost
9,900 Cr
Current cost
11,000 Cr
Timeline
- Construction startMar 2018
- Original completion targetDec 2024
- Current completion targetJul 2025
Tenders and Contracts
NIT: BMRCL/Phase-2/Pink/UG/02
Cost: ₹2100 Crawarded
Design and Construction of Twin Tunnels and 12 Underground Stations for Pink Line
Funding and Sources
- Operator
- Bangalore Metro Rail Corporation (BMRCL)
- Funding source
- mixed
- Source
- [Bangalore Metro Rail Corporation Limited (BMRCL)]Source Reference ↗Official Releasehigh Confidence