Bangalore/Metro/Under Construction

Namma Metro Yellow Line — RV Road to Bommasandra

18.82 km elevated corridor through South Bangalore connecting RV Road to Bommasandra via Jayanagar and BTM Layout. 16 stations.

Key Facts

Status

Under Construction

Mode

Metro

Length

19 km

Stations

18

Progress

61%

Expected completion

Jul 2025

Approved cost

7,610 Cr

Current cost

7,610 Cr

Timeline

  1. Construction startMar 2017
  2. Original completion targetDec 2021
  3. Current completion targetJul 2025

Recent Updates

Tenders and Contracts

NIT: BMRCL/Phase-2/Yellow/Viaduct/01
Cost: ₹761 Crawarded

Design and Construction of Elevated Viaduct and 16 Stations for Yellow Line

Floated: Jun 15, 2017
Awarded: Nov 20, 2017
Contractor: L&T Construction (Chennai, Tamil Nadu)

Funding and Sources

Operator
Bangalore Metro Rail Corporation (BMRCL)
Funding source
mixed
Source
[TIMESOFINDIA]Source Reference
News Mediamedium Confidence