Mumbai Metro Line 3 — Aarey to BKC Phase 2

Remaining 12 stations of Mumbai Metro Line 3 (Aqua Line) from Dharavi to Aarey. Fully underground corridor. Phase 1 (Aarey–BKC) operational since October 2024.

Key Facts

Status

Testing

Mode

Metro

Length

33.5 km

Stations

27

Progress

82%

Expected completion

Jul 2025

Approved cost

23,136 Cr

Current cost

37,276 Cr

Timeline

  1. Construction startJun 2016
  2. Original completion targetApr 2024
  3. Current completion targetJul 2025