Mumbai Construction Projects
Structured transit project data for India with delay and cost deltas that can be cited.
Total projects tracked
3
Under construction
1
Total km under construction
3.2 km
Avg delay
15 mo
Ranked Project Table
Most delayed projects first. Click any column header to re-sort.
Current tracked cost: 50,776 ₹Cr
| Mumbai | Mumbai Metro Line 2A — Dahisar to DN Nagar ↗Mumbai Metropolitan Region Development Authority (MMRDA) | Metro | Open | Apr 2022 | Jul 2023 | 1 yr 3 mo | 18.6 km | 13,500 | 7% |
| Mumbai | Mumbai Metro Line 3 — Aarey to BKC Phase 2 ↗Mumbai Metro Rail Corporation (MMRC) | Metro | Testing | Apr 2024 | Jul 2025 | 1 yr 3 mo | 33.5 km | 37,276 | 61% |
| Mumbai | Mumbai Metro Line 7A — Andheri East to CSIA Airport T2 ↗Mumbai Metropolitan Region Development Authority (MMRDA) | Metro | Under Construction | Dec 2026 | Jul 2026 | On track | 3.2 km | — | — |