Cabinet-approved combined scope
58.19 km
Length source: Cabinet approves Bangalore Metro Rail Project Phase 2A and Phase 2B
Source-backed construction dossier
Bengaluru · Metro · Under construction · Bangalore Metro Rail Corporation Limited (BMRCL)
Last reviewed: 2026-07-17 · June 2026 reporting context; reported targets are not completion guarantees.
Cabinet-approved combined scope
58.19 km
Length source: Cabinet approves Bangalore Metro Rail Project Phase 2A and Phase 2B
Combined approval cost
₹14,788.101 crore
Cost source: Cabinet approves Bangalore Metro Rail Project Phase 2A and Phase 2B
Combined stations
30
Station source: India, ADB sign $500 million loan to expand Metro Rail Network in Bengaluru
The ADB loan release describes a differing 56 km scope for two new lines with 30 stations. It is shown as a source conflict/differing scope, not silently reconciled with the Cabinet's 58.19 km approval scope.
India, ADB sign $500 million loan to expand Metro Rail Network in Bengaluru
Nineteen accepted claims are shown in deterministic order. Classifications are written as text, and unknown fields remain explicitly unsupported.
Publisher: Press Information Bureau
Source type: official · Published: 2021-04-20 · Retrieved: 2026-06-27
Interpretation: Cabinet approval source supports the combined programme scope; it is kept separate from the differing ADB scope.
Publisher: Press Information Bureau
Source type: official · Published: 2021-04-20 · Retrieved: 2026-06-27
Interpretation: Cabinet approval source supports the combined approval cost.
Publisher: Press Information Bureau (Ministry of Finance)
Source type: official · Published: 2021-08-23 · Retrieved: 2026-06-27
Interpretation: ADB source supports the combined two-line station count; phase-level counts remain unknown.
Publisher: Press Information Bureau (Ministry of Finance)
Source type: official · Published: 2021-08-23 · Retrieved: 2026-06-27
Interpretation: ADB source describes a differing source scope; it is not reconciled with the Cabinet scope.
Publisher: The Hindu
Source type: news · Published: 2026-06-19 · Retrieved: 2026-07-17
Publisher: The Times of India
Source type: news · Published: 2026-06-20 · Retrieved: 2026-07-17
Interpretation: Accepted milestone reports October 2026 as a target, not a completion guarantee.
Publisher: The Hindu
Source type: news · Published: 2026-06-19 · Retrieved: 2026-07-17
Interpretation: Accepted milestone reports June 2027 as a target, not a completion guarantee.
Publisher: The Hindu
Source type: news · Published: 2026-06-19 · Retrieved: 2026-07-17
Publisher: The Times of India
Source type: news · Published: 2026-06-20 · Retrieved: 2026-07-17
Interpretation: Accepted milestone reports December 2027 as a target, not a completion guarantee.
Publisher: Press Information Bureau
Source type: official · Published: 2021-04-20 · Retrieved: 2026-06-27
Publisher: Press Information Bureau (Ministry of Finance)
Source type: official · Published: 2021-08-23 · Retrieved: 2026-06-27
Publisher: Bangalore Metro Rail Corporation Limited
Source type: dpr · Published: Date unavailable · Retrieved: 2026-06-27
Publisher: The Hindu
Source type: news · Published: 2026-06-19 · Retrieved: 2026-07-17
Publisher: The Times of India
Source type: news · Published: 2026-06-20 · Retrieved: 2026-07-17
Interpretation: The accepted programme record is retained in manual-entry order with all of its supporting source refs.
Publisher: Press Information Bureau
Source type: official · Published: 2021-04-20 · Retrieved: 2026-06-27
Publisher: Bangalore Metro Rail Corporation Limited
Source type: dpr · Published: Date unavailable · Retrieved: 2026-06-27
Interpretation: The accepted Phase 2A record is retained in manual-entry order with all of its supporting source refs.
Publisher: Press Information Bureau
Source type: official · Published: 2021-04-20 · Retrieved: 2026-06-27
Publisher: Press Information Bureau (Ministry of Finance)
Source type: official · Published: 2021-08-23 · Retrieved: 2026-06-27
Publisher: Bangalore Metro Rail Corporation Limited
Source type: dpr · Published: Date unavailable · Retrieved: 2026-06-27
Interpretation: The accepted Phase 2B record is retained in manual-entry order with all of its supporting source refs.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. Exact breakdown of 58.19 km into Phase 2A vs Phase 2B lengths is not cited in available sources. Individual phase lengths must not be invented.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. Individual phase costs are not available from the allowed sources. Do not divide the combined Rs. 14,788.101 crore figure across phases without additional sourcing.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. Station count of 30 is from the ADB loan release and refers to the combined two-line scope. Individual phase station counts are not available from allowed sources.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. No package details, package codes, contractors, contract awards, or package-specific timelines are available from accepted sources.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. No package details, package codes, contractors, contract awards, or package-specific timelines are available from accepted sources.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. No package details, package codes, contractors, contract awards, or package-specific timelines are available from accepted sources.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. Current cost escalation beyond the approved Rs. 14,788.101 crore is not available.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. Neither construction start date nor guaranteed completion date for the overall programme or individual phases is available from the allowed sources.
No source link. The accepted packet does not support this field.
Interpretation: The accepted packet does not support this field. Neither construction start date nor guaranteed completion date for the overall programme or individual phases is available from the allowed sources.
Parent programme
The Blue Line is an under-construction metro corridor from Central Silk Board Junction to Kempegowda International Airport via K.R. Puram and Hebbal, implemented as Phase 2A and Phase 2B. The Union Cabinet approved the combined 58.19 km scope on 20 April 2021 at Rs. 14,788.101 crore, while the ADB loan release describes a 56 km loan scope. Secondary reporting of a June 2026 ministerial review—not an official BMRCL publication—reported target trial runs and section dates; all remain targets rather than guaranteed completion dates.
Status: under construction · Operator: Bangalore Metro Rail Corporation Limited (BMRCL)
Phase 2A
Phase 2A runs from Central Silk Board Junction to K.R. Puram. It was approved as part of the combined Cabinet scope, and the BMRCL executive summary identifies it as under implementation. Phase-specific length, cost and station totals remain unknown.
Status: under construction · Operator: Bangalore Metro Rail Corporation Limited (BMRCL)
Phase-level length, cost, and station totals: Unknown.
Phase 2B
Phase 2B runs from K.R. Puram to Kempegowda International Airport via Hebbal Junction. It was approved as part of the combined Cabinet scope, the ADB loan supports the overall two-line programme, and the BMRCL executive summary identifies it as under implementation. Phase-specific values remain unknown.
Status: under construction · Operator: Bangalore Metro Rail Corporation Limited (BMRCL)
Phase-level length, cost, and station totals: Unknown.
Every displayed claim resolves to the packet's accepted source index.
Cabinet approval covered the combined 58.19 km scope at Rs. 14,788.101 crore.
ADB loan source describes two lines totaling 56 km; this differs from the Cabinet approval scope.
BMRCL Phase 3 DPR executive summary states Phase 2A and 2B are under implementation; no start date is claimed.
Secondary reporting of the ministerial review described Phase 2A trial runs targeted from October 2026, Hebbal–Airport targeted for June 2027, and KR Pura–Hebbal targeted for December 2027. These are targets, not completion guarantees.
Cabinet approval covers the combined Phase 2A and Phase 2B scope.
BMRCL executive summary states Phase 2A is under implementation.
Cabinet approval covers the combined Phase 2A and Phase 2B scope.
ADB loan supports the combined two-line programme; phase allocation is not claimed.
BMRCL executive summary states Phase 2B is under implementation.
Secondary reporting of the ministerial review described Phase 2A trial runs targeted from October 2026, Hebbal–Airport targeted for June 2027, and KR Pura–Hebbal targeted for December 2027. These are targets, not completion guarantees.
These are secondary-reporting targets, not guaranteed completion dates.
The packet does not support phase-level length, cost, or station totals, current cost, a guaranteed completion date, a construction start date, packages, contractors, or contract awards. These fields remain Unknown.
Bengaluru Metro Blue Line (ORR-Airport Metro) is derived from the accepted manual-entry packet. It does not claim phase-level values or live construction progress; the accepted source index and field limitations are shown above.